Sullivan’s Creek Cycle Path Crossing

Package 2 | 2016

Works |  included the construction of a new wombat crossing and widening of the existing path at Goodwin St and upgrades to the signage and street-lighting at Deburgh St. These works allowed pedestrians and cyclists safe crossing of these highly trafficked roads. This upgrade provides an improvement to public safety, pedestrian and cyclist movements and imrpoves the travel time along the busy shared path.

Goodwin Street works included:

• the closure of Goodwin Street
• removal and demolition of existing road pavement;
• construction of a red oxide 200mm wombat crossing;
• construction of pram ramps;
• widening of the shared path either side of the crossing;
• protection of trees;
• installation of new street-lighting
• line-marking and signage

Goodwin Street | December 2016

De Burgh Street works included:

• removal, modification and installation of signage for the crossing
• trimming of trees to improve sight lines
• street-lighting upgrade and improvements
• upgrade of line-marking and crossing piano key markings

De Burgh Street | December 2016